Power
A transmission line appears near the parcel
What this supports: a potential infrastructure lead, if its location and identity are verified.
What remains unknown: connection feasibility, spare capacity, reinforcement costs and energization date.
Next action: seek a project-specific utility response. Do not label the parcel “power-ready”.
Water
Seasonal wetness is visible on part of the site
What this supports: a drainage or ground-condition question where image quality and dates are suitable.
What remains unknown: wetland status, seasonal flood conditions, permissible works and net buildable area.
Next action: compare authoritative mapping and obtain local field review. Wet ground does not establish a usable cooling-water supply.
Planning
A development approval is published
What this supports: the specific decision described in that document.
What remains unknown: outstanding conditions, separate permits, utility commitments and later changes.
Next action: create an approval-and-conditions register. Do not convert one approval into an all-clear result.